Saturday, July 20, 2013

FIRST SHIFT CANCELLED FOR MONDAY

Due to the extended power outage created by yesterday's powerful storms, there will NOT be production on first shift Monday, July 22nd as we work to get the plant back online. Production will begin with second shift on Monday. Only first shift's production team is off -- 1st shift's management, administrative, shipping, set-up, maintenance, machining and secondaries personnel should still report to work on Monday. The production personnel who will be unable to work can make up their time on Saturday when the split shift will be working. Likewise, anyone who was unable to work today because of the outage will have a chance to work on a Saturday when their team is not scheduled to.